Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Monitoring of SPI in a Project

1 reply [Last post]
Kannan CP
User offline. Last seen 24 weeks 1 day ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

At what stage in a Project, the monitoring of SPI should be stopped,

1. is it after the baseline program completion date is over, but still with works ongoing in delay. 

2. or earlier, noticing that project is in significant delay and will not meet target.

Regards

Kannan

Replies

Peter Holroyd
User offline. Last seen 4 days 22 hours ago. Offline
Joined: 6 Jun 2005
Posts: 166

When it is easier to do a resourced contract close out list (inc snagging). Use JIRA (or similar) and burn down those actions!

Patrick Weaver
User offline. Last seen 6 days 13 hours ago. Offline
Joined: 18 Jan 2001
Posts: 384
Groups: None

Traditional SPI becomes increasingly unreliable after the mid point of the project - certainly in the last third as it trends back towards 1.0.  It is also a relatively meaningless number all changes in SPI can tell you is there has been as change in the values used to calculate the ratio.  

If you are looking for a realistic projection of completion based on Earned Value Management (EVM) data, consider using Earned Schedule (ES) the concept has been around for nearl 20 years now and the tools are free to access and use. All you need to to transpose your EVM data into the calculator. 

For more on ES see: https://mosaicprojects.com.au/PMKI-SCH-040.php#Process2