Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

What is a good labor cost factor % to go to 10hrs/from 8 and 6 dy wk instead of 5 dy wk. = Premium time

2 replies [Last post]
John Reeves
User offline. Last seen 2 weeks 6 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

In theory, it shouldn't be that much more because you complete the same work faster.  If you are going from 40 to 50 during the week, possibly the same resource couldn't work the Sat.  But lets assume it does.  Does this mean x 1.5 factor x 1/3 of the hours - because 40 of the 60 would be straight time leaving 1/3 of the hours x 1.5.  What do you think?  I understand we could and should look up the rates per trade etc, this is just to be an estimate against budgeted cost to accelerate.

Replies

Peter Holroyd
User offline. Last seen 4 hours 17 min ago. Offline
Joined: 6 Jun 2005
Posts: 164

John,

you need to look at their trade working rule agreements for the cost factors as opposed to the productivity (output) rates.

We found that some agreements for instance give a second 0.5 hr pm break for a 10 hr day shift as opposed to a 10 min tea break on a 8 hr day shift. Others allowed the breaks to be taken (or not) at the end of the day shift. Other work agreements insist on doing the 40 hours before you were eligible to do the o/t.

If you want generalisation - these might be applied

                               Output/hr          Cost

8 hr x 5 day shift         1.0                1.0

10hr x 5 day shift         1.0                1.1

10hr x 6 day shift         0.9               1.25

12hr x 5 day shift          0.8              1.5

12 hr x 5 night shift       0.7              2.5

9 day x 10 hr rotating shift 0.9          1.25

Could well be a diference if you want CtE rather than Manpower costs and need to add in additional supervision costs.

Peter

Peter Holroyd
User offline. Last seen 4 hours 17 min ago. Offline
Joined: 6 Jun 2005
Posts: 164

John,

you need to look at their trade working rule agreements for the cost factors as opposed to the productivity (output) rates.

We found that some agreements for instance give a second 0.5 hr pm break for a 10 hr day shift as opposed to a 10 min tea break on a 8 hr day shift. Others allowed the breaks to be taken (or not) at the end of the day shift. Other work agreements insist on doing the 40 hours before you were eligible to do the o/t.

If you want generalisation - these might be applied

                               Output/hr          Cost

8 hr x 5 day shift         1.0                1.0

10hr x 5 day shift         1.0                1.1

10hr x 6 day shift         0.9               1.25

12hr x 5 day shift          0.8              1.5

12 hr x 5 night shift       0.7              2.5

9 day x 10 hr rotating shift 0.9          1.25

Could well be a diference if you want CtE rather than Manpower costs and need to add in additional supervision costs.

Peter