Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Histogram :Manpower & Machineries

4 replies [Last post]
Suhaila Tsu
User offline. Last seen 49 weeks 2 days ago. Offline
Joined: 6 Jun 2011
Posts: 25

Dear Experts

 

Can we produce manpower & machineries histogram from p6?

if can, how to?

 

Thank u

Replies

Zoltan Palffy
User offline. Last seen 2 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

use 2 different types of resources one for labor and the other for non-labor aka equipment

then for each activity that labor element assign a labor resource and then assign the budgeted manhours to perform that activity

then for each activity that has an equipment element assoicated with it assign the particular piece of equipment to it

Rafael Davila
User offline. Last seen 1 week 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

The same goes for equipment such as a single Tower Crane. To avoid chaos make sure you do not over-load this resource; easy, resource level part-time assignments.
2021-09-25-06-20-46

  2021-09-25-06-22-11
 

Rafael Davila
User offline. Last seen 1 week 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

To my understanding P6 is very poor at disclosing manpower quantity (ea), in any case effort (hours), different parameters with different unit of measure.

Man Power | Definition of Man Power by Merriam-Webster

  • usually manpower : the total supply of persons available and fitted for service

Calculating the required quantity from effort units is not always easy, a simple conversion factor will not make it.  An average makes sense only when all resources are busy all the time, otherwise you might under/over estimate the required quantity. Communicating a resource plan by only using effort is not good enough.
  2021-09-24-13-17-20

2021-09-24-08-20-19

Rodel Marasigan
User offline. Last seen 1 day 9 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Hi Suhaila,

Yes you can. If your schedule is resource loaded with labor (manpower) & nonlabor (machineries) then you can produce the histogram report. See step below:

Step 1: On Activity window click the activity profile icon. At the right side bottom layout of the screen, it wil show the activity usage profile graph.
Step 2. Right click on the graph and select activity usage profile options. Select Unit for Display and Select Labor for Bar/Curves. Select Budgeted by date for Bars and select Plan Value Labor Unit for Cummulative as shown below.
Activity-Profile-Option

Step 3. Click Graph Tab. Click Calculate Average and enter the total number of hour per time period per selected timescale Ex: timescale = month = 10hr/day Mon->Fri and 5hr Sat = 55hr/week * 52 weeks (in a year)/ 12 months = 238.33 say 238. If your admin preference time period is setup as use assign calendar time period is tick you can tick Base on Hours per Time Period and it will calculate automatically. If you don't have admin right and you are using multiple calendar then I recommended to type manually to make sure as shown below.

Activity-Profile-Option2

Step 4. Click Ok and it should gave you the histogram.

Step 5. If you want to see the number table against histogram click View--> Show On Top--> Activity Usage Spreadsheet. Then colapse the to project summary then righ click and select spreadsheet options and enter same number enter on usage profile and it show you the histogram as per sample below.Sample-Histogram

You can also use Resource Usage Profile if you wanted to select only the resouces you want to show on the histogram or you can select all resources assign to project per resource type. Using resource usage profile is more flexible and you can also Show a Stacked Histogram as shown below:
Manning-Histogram

Steps in showing Stacked Histogram
Step 1. Select Resource Usage Icon.

Step 2. Right Click on the Graph and select Stacked Histogram

Step 3. Right Click again and select Resource Usage Profile Options

Step 4. Select Graph Tab and select show value, click Calculate Average and enter the number of hours per time period per timescale then click apply.

Step 5. Select Data Tab and click Add. You have to create a filter per group category on your resources. On below sample I have a resource group by discipline.

Filter-Discipline