Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Connecting P6 with Submittal Log and Schedule of Values - any good ways or spreadsheet systems?

1 reply [Last post]
John Reeves
User offline. Last seen 2 weeks 3 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Connecting P6 with Submittal Log and Schedule of Values - any good ways or spreadsheet systems? - These items are intertwined - one of the worst things you can do is make the schedule into either a submittal log (or a to do list).  But how to you efficiently feed the info between them - surely P6 has addressed this.  I think years ago they did with their Old CM tools (ie Expedition - yes I am old.) but by getting fancier I think that easy link was lost.  I only see them excel now days.

Replies

Zoltan Palffy
User offline. Last seen 2 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

the old expedition is not Primivera Contract Manager and you can inport of there into excel.

The other option is to build a submittal log yourself by using the p6 import spreadsheet