Connecting P6 with Submittal Log and Schedule of Values - any good ways or spreadsheet systems?

J
John Reeves 👤 Member for 13 years 2 months

Connecting P6 with Submittal Log and Schedule of Values - any good ways or spreadsheet systems? - These items are intertwined - one of the worst things you can do is make the schedule into either a submittal log (or a to do list).  But how to you efficiently feed the info between them - surely P6 has addressed this.  I think years ago they did with their Old CM tools (ie Expedition - yes I am old.) but by getting fancier I think that easy link was lost.  I only see them excel now days.

Z
Zoltan Palffy 👤 Member for 17 years

the old expedition is not Primivera Contract Manager and you can inport of there into excel.

The other option is to build a submittal log yourself by using the p6 import spreadsheet

Featured Partner

Top Posters

MR JUDE C ANYAEGBU
0 posts
GeoVe
0 posts
Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts