Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Rate of Placement

1 reply [Last post]
Heather Hadley
User offline. Last seen 1 year 41 weeks ago. Offline
Joined: 29 Jan 2019
Posts: 27
Groups: None

Hi All,

I'm looking for a table that gives the rates of placement for industrial construction - example how many hours does it take to put in a cubic meter of concrete (generally).  I looked through the forum and found a couple of links that don't work anymore.  Can anyone point me in the right direction?

TIA!

Replies

Zoltan Palffy
User offline. Last seen 16 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

on this site up top there is a tab called Build Times

http://www.planningplanet.com/wiki/422384/rates-norms-durations