Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Reporting Wizard

6 replies [Last post]
Planner Planner
User offline. Last seen 4 years 16 weeks ago. Offline
Joined: 21 Jul 2015
Posts: 12
Groups: None

Dear Forum Members.

Could you please explain me where we use below mention function in report wizard window.

What is show prior/post function mean?

 

7335
capture.png

Replies

Zoltan Palffy
User offline. Last seen 20 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

need your email address to do that 

Planner Planner
User offline. Last seen 4 years 16 weeks ago. Offline
Joined: 21 Jul 2015
Posts: 12
Groups: None

I could not open image that you attached please send it to me 

Planner Planner
User offline. Last seen 4 years 16 weeks ago. Offline
Joined: 21 Jul 2015
Posts: 12
Groups: None

Many thanks

Planner Planner
User offline. Last seen 4 years 16 weeks ago. Offline
Joined: 21 Jul 2015
Posts: 12
Groups: None

......

Zoltan Palffy
User offline. Last seen 20 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None
  • 7340
    zcapture.jpg
  •  
  • Show Time intervals
    This option displays the spread for the data item (selected under Time Interval Fields button in above dialog) for each time interval (selected under Timescale button in above dialog) from the timescale start date to the timescale finish date (selected under Timescale button in above dialog).
    In the report above we have selected to display the Remaining Units by week for the month of November.
     
  • Show Prior
    This option displays the cumulative value before the first time interval.
    In the report above, the Project Manager had accumulated 40 days and 4 hours of Remaining Units before the first week in November.