Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Testing and Commissioning Labour

4 replies [Last post]
Mike planner
User offline. Last seen 2 years 43 weeks ago. Offline
Joined: 3 Feb 2011
Posts: 46
Groups: None

Hello, 

 

i just produced a labour histogram for the testing and commissioning labour histograme, basically, i apply 1 manday to each testing and commissiioning activities. 

The natural of the project is refurbishment, fit-out, plantrooms and testing and commssioning. 

The peak TOTAL labour resources is about 110 labour. 

the peak of my testing and commissioning labour is about 18 men

Does it sounds right, too high? or just ok? 

 

7176
capture.png

 

Many thanks

Mike 

Replies

Rafael Davila
User offline. Last seen 2 weeks 14 hours ago. Offline
Joined: 1 Mar 2004
Posts: 5241

"...the peak of my testing and commissioning labor is about 18 men...basically, I apply 1 man-day to each testing and commissioning activities."

  • Do you mean one person the full day for each activity for the duration of each activity?
  • What is the reasoning for such resource loading?

I would expect testing and commissioning activities to be performed by several teams, each team using several resources and perhaps because of resource availability leveling might delay some activities.

It is also possible that some resources might be on partial assignments or "part of the time" allowing for the same resource be working on several activities on the same day.

Jonathan Goldsmith
User offline. Last seen 4 years 47 weeks ago. Offline
Joined: 4 Dec 2019
Posts: 6
Groups: None

There is a lot more information needed. I'm not sure if this adds anything to the conversation or not, but I would start by asking some more specific questions. For instance:

What does your team say? What do your upers think?

What do the subcontractors say? What do their supers think?

Who's doing the commissioning?

Will they need superviosion?

An probably the most important question: Is there enough supervision to make sure the assigned people are working efficiently?

 

Good luck!

-Jon

Rafael Davila
User offline. Last seen 2 weeks 14 hours ago. Offline
Joined: 1 Mar 2004
Posts: 5241
  • Because P6 does not account for resource quantities but effort you might be getting wrong numbers.
  • How did you calculated the quantity? 

By the way the image is illegible, I cannot read the headings and values.

Best Regards,

Rafael

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

that depends on what you are commissioning and the levels of testing that you are doing.