How do you show 3 baselines on one bar?

7 replies [Last post]
Philip James
User offline. Last seen 1 year 21 weeks ago. Offline
Joined: 20 Mar 2016
Posts: 20
Groups: None

Hi

My manager has asked me to show 3 baselines on one bar. Shown me the output

 

One bar for one activity, with 3 colours per baseline overlapping to show delay - rather than the usual stack arrangment

Replies

Zoltan Palffy
User offline. Last seen 8 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

glad I could help 

Philip James
User offline. Last seen 1 year 21 weeks ago. Offline
Joined: 20 Mar 2016
Posts: 20
Groups: None

Worked it out. Filter the bars by PS and CD 

Philip James
User offline. Last seen 1 year 21 weeks ago. Offline
Joined: 20 Mar 2016
Posts: 20
Groups: None

6193
capture.jpg

Philip James
User offline. Last seen 1 year 21 weeks ago. Offline
Joined: 20 Mar 2016
Posts: 20
Groups: None
Thank you In poorly explaining it. I know I need to filter the bars....so you can only see the delay
Zoltan Palffy
User offline. Last seen 8 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

then put them all on the same row number. this is not the correct way to do it but its your call i am just telling you how to do what you want.

Philip James
User offline. Last seen 1 year 21 weeks ago. Offline
Joined: 20 Mar 2016
Posts: 20
Groups: None
Cheers. Oh. The picture isn't there... I do want them overlapped I want one bar that goes up to a point with the baseline date, then goes further with the update and to the end with the last update (poorly explained I know)
Zoltan Palffy
User offline. Last seen 8 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

1st maintain and assign 3 baselines 

then in the gantt area right click bars and select the primary baseline, the seconday basline and the tertiary basline  

make sure that each of these has their own row number (listed under Pattern) or they may be on top of one another.