Programme Forecast

Member for

16 years 3 months

an S-curve typically deals with resources. I think that the client is looking for a TIA time impact analysis which meands adding the delay into the schedule and showing the activities and logic that was added to impacted the schedule in a graphical Gantt chart or time scaled logic diagram.

Member for

19 years 10 months

Hi Debosky

When you add progress to a programme you set data date with a dropline that sets the date of the progress report.

The drop line can be Zig Zag or straight.

When the progress is added and the dropline is straight then the actual completion date is revealed when rescheduled

You can set up 2 colums that shows planned completion and actual completion.

This data can then be extracted to a spreadsheet and you can create youe s-curve.

I trust that is clear enough.

Best regards

Mike Testro

Member for

11 years 3 months

Hello Mike,

Thank you so much for your help.

To be honest, I don't understand what you meant, can you please elaborate more, please ?

 

Regards,

Member for

19 years 10 months

Hi Debosky
The usual and simplest way is to set the dropline to vertical and re schedule.
Best regards
Mike Testro