an S-curve typically deals with resources. I think that the client is looking for a TIA time impact analysis which meands adding the delay into the schedule and showing the activities and logic that was added to impacted the schedule in a graphical Gantt chart or time scaled logic diagram.
Member for
16 years 3 monthsan S-curve typically deals
an S-curve typically deals with resources. I think that the client is looking for a TIA time impact analysis which meands adding the delay into the schedule and showing the activities and logic that was added to impacted the schedule in a graphical Gantt chart or time scaled logic diagram.
Member for
19 years 10 monthsHi DeboskyWhen you add
Hi Debosky
When you add progress to a programme you set data date with a dropline that sets the date of the progress report.
The drop line can be Zig Zag or straight.
When the progress is added and the dropline is straight then the actual completion date is revealed when rescheduled
You can set up 2 colums that shows planned completion and actual completion.
This data can then be extracted to a spreadsheet and you can create youe s-curve.
I trust that is clear enough.
Best regards
Mike Testro
Member for
11 years 3 monthsHello Mike,Thank you so much
Hello Mike,
Thank you so much for your help.
To be honest, I don't understand what you meant, can you please elaborate more, please ?
Regards,
Member for
19 years 10 monthsHi Debosky The usual and
Hi Debosky
The usual and simplest way is to set the dropline to vertical and re schedule.
Best regards
Mike Testro