Hello All,
I would like to understand / learn more how my fellow planners manage baseline change on Project -
1. What factors beyond the usual (Scope / Contract / Resource / Budget ) determine a change to the baseline? for example would low productivity rate constitute a baseline change?
2. Does one normally do a What-if scenario in P6 to determine whether or not to go ahead with the baseline change? If so do you use original baseline file which OR Most recent Statussed file?
3. How does one mimic changes made to the baseline file in to the most recent statussed file. What checks and crieteria does one use in P6 to ascertain that the historical Earnings was not changed? (I have usually done replication manually but it takes a lot of time if the baseline change is a complex one, hence would like to get feedback from you all on what could a effiecient way be to handle a change)
Thanks in advance
SD
Replies