Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Step By Step Procedure for Recovery Schedule - Reg

1 reply [Last post]
Umashankar Vijayan
User offline. Last seen 6 years 24 weeks ago. Offline
Joined: 5 Sep 2012
Posts: 2
Groups: None

Dear All,

This is Umashankar Presenting greetings of the season!

I am currently involved in producing a revised schedule.  The Project has a contract duration of 3 years; of which 1 1/2 years is already elapsed.  The client issued a Variation Order for descope and the Contract Completion date still remains the same.  

With this scenario, I am forced to produce a revised schedule on the date of VO issued.  The revised programme shall be produced in a different execution strategy as that of baseline programme due to change in Traffic Diversion Scheme post approval of Baseline Programme.

Hence I have to make the schedule to reflect the actuals until VO issue date, i.e., 

For Completed Activities:

Original Duration = Actual Duration

Planned Start and Finish Dates = Actual Start and Finish Dates

For in Progress Activities:

Original Duration = Actual Duration + Remaining Duration

Planned Start = Actual Start

Planned Finish = Finish

Until this step everything went well; but there was no effect to the earned values, i.e. Planned Value cost and Earned Value cost doest not match.

 

Can anyone suggest how to make the Budgetted Cost, Planned Value Cost and Earned Value Cost equal before doing any changes to the Programme?

 

Thanks in Advance,

V. Umashankar.

Replies

Zoltan Palffy
User offline. Last seen 17 weeks 13 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

run a global change to make them equal