Unit mhrs

1 reply [Last post]
ronron martinez
User offline. Last seen 7 years 27 weeks ago. Offline
Joined: 19 Nov 2009
Posts: 41

Dear ALL,

For the contruction planning what will be the right method on the manpower histogram.

Do i need to basing the unit man hour from the contract B.O.Q or from the manpower estimation on each activity.

Any advise please...

Regard's

Ron

Replies

Zoltan Palffy
User offline. Last seen 16 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

If you have the manpower estimate for each activity then you have the total is the Budgeted Quantity