Hi all,
May i request you time to get some explanation regarding the design and the procurement in a major puming statiion. My understanding is like as follows,
1. For the design works, the main contractor will make the Process Flow Diagram(PFD) and the P&ID will follow.
2. The vendor will prepare the design of the major equipments(like pumps, transformers etc) based on the contract specification provided by the main contractor.
3. The P&ID can be finalised based on the input from the vendor(to show the data sheet details of equipments) and the hydraulic design.
4. Hydraulic design can start after the PFD, along with the P&ID.
5. The size and material of the piping in the P&ID will be decided by the main contractor's design team( required hydraulic design completion). Based on this finalized P&ID, the line list, piping layout & isometric drawings will be prepared by the main contractor. Then the vendor will prepare the shop drawings and can start the manufacturing of the pipes.
6. Electrical single line drawings, general layout, Junction box/socket schedules etc will be prepared/decided by the main contractor. or is there any design which will decide the no of junction boxes/panels etc?. I understand that the main contractor will select the supplier for this junction boxes and other minor items with an RFQ. Then the material submittal/approval and the commencement of manufacturing.
Please, anyone having experience in this sector share their views
Thanks
Kannan
Replies