distributing staff on the schedule

1 reply [Last post]
moutaz aldeib
User offline. Last seen 3 years 2 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Dear Planners,

I have a schedule on MS Project 2010, and I would like to assign the resources, one of the problems I am facing is that:

I have 6 engineers with their salaries and WF on that project, how to distribute them on the schedule?

Regards,

Moutaz

Replies

Raymund de Laza
User offline. Last seen 5 days 18 hours ago. Offline
Joined: 22 Nov 2009
Posts: 762

Create a Resource Dictionary using the Names of the Engineers with their corresponding details such as rates and Working Calendars then assign them to their corresponding Activities.