Unassigned baseline problem with current project

1 reply [Last post]
müjdat özacar
User offline. Last seen 5 years 32 weeks ago. Offline
Joined: 30 May 2009
Posts: 13

Hi All,

Although i havent assigned any baseline to my schedule in bar chart i see baseline bars(project,primary or secondary) for actual activities seen attached picture

When i assign baseline i also see same bars

1954
baseline.png

Can anybody help me?

Replies

Ronald Winter
User offline. Last seen 3 years 36 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

Mujdat,

That is how it is supposed to work.  The manual states that if no baselines are assigned, then the Planned Start and Planned Finish dates in your current schedule will be used.  It also states that once a baseline is saved and assigned, that the baseline schedule Planned Start and Planned Finish date will be used.  If no status has been assigned since you assigned the baseline schedule, then those dates would be the same.  Good luck!