Dear All,
this topic may be be more related to Primavera P6 but i posted this one here since more experienced project controller are active in this forum.
Problem Summary
---------------------------------------------------
differences bt BL budget & act. for past periods when converting and assigning current project as ba
Problem Description
---------------------------------------------------
Problem description:
1- I converted the current project as baseline and assign it to the project.
2- in the administration Earned value setting I choose either of one of the options "Planned Value with current date" or " At completion values with current dates"
3- I expect that the baseline schedule bars to be same as the current schedules bars which is correct no problem on that.
4- I also expect that past period actual and BL Budget be the same up to data date point) and the balance budgeted values (or units) to transfer to remaining period of each activities but this is not what happening in P6.
In another word when we revise a plan in certain data date the actual and planned should be same at data date, and from that time onward we will plan for the progress of remained activities of the project.
the differences are coming from the "in progress activities" and the values for completed activities are same and correct.
would you kindly check and let me know what is your idea about that?