Man Hours

1 reply [Last post]
Ammar Tauqeer
User offline. Last seen 10 years 48 weeks ago. Offline
Joined: 6 Oct 2013
Posts: 22

I've completely tracked my project now i want to know my actual manhours how can i know that?

Replies

Mike Testro
User offline. Last seen 36 weeks 3 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Amnar

What method did you use to allocate resources to your task bars?

If your modelling is based on duration = man hours / gang size then it is easy to create a graph of both planned v achieved man hours.

Best regards

Mike Testro