Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Project Variance Log Document

5 replies [Last post]
Ars J
User offline. Last seen 9 years 29 weeks ago. Offline
Joined: 1 Mar 2013
Posts: 8
Groups: None

Dear All,

Please support me with a sample of Project Variance Log Document.

Thank you very much.

Replies

Ars J
User offline. Last seen 9 years 29 weeks ago. Offline
Joined: 1 Mar 2013
Posts: 8
Groups: None

Dear Rafael,

Thnx for your help.

this document shall be submited within change order document. I already designed it.

I hope client approves or at least I recieve good comments on it.

Best Regards,

Arsalan

Rafael Davila
User offline. Last seen 2 weeks 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5230

Arsalan,

At home for such document(s) we do not use the term variance. We know them by their function as there are so many and among others name them:

  1. Change Orders and Directives Log
  2. Drawings Log
  3. Endorsements (usually procured by Client) and Permits (usually procured by Contractor) Logs
  4. Insurance Status Log - to follow up status of Contractor and Subcontractor's Workmen Compensation Insurance and other insurances such as the Comprehensive Liability and Automobile Insurances that might expire during the course of the job.
  5. Issues Log - Can include among others Notices to Comply and other Pending Items to follow up that are not under other log.
  6. Rain Days Log
  7. RFI - Request for Information Log
  8. RFP - Request for Proposals Log
  9. Project Close Out Check List - Some keep/name it as a Log
  10. Project Status Log - usually updated with the schedule to include a summary of current Baseline versus Current update. Include summary items for Current versus Baseline: BOQ costs, percentage complete, remaining project duration, status of payments among a few others.
  11. Purchasing and Deliveries Log - usually for the use by the Contractor
  12. Safety Meetings and Notices Log
  13. Test Results Log
  14. Transmittals Log
  15. Visitor's Log

  Most of these documents are of great value to the scheduler as they provide items and dates that must be used on the schedule updates as well as on delay analysis schedules.  I must assume every construction scheduler know most of them, still there are a few that might not be so well known such as the Endorsements and Permits Log.

At home it is not unusual for our jobs be delayed by reason of Endorsement and Permits issues that we find it useful to keep these under a separate log.  Some logs such as the Concrete Test Log can be used to re-construct and verify schedule dates.

I suggest you download some samples from the web by doing a search using their specific names and hope the provided names can be of some help.  Another source can be to look at the pre defined logs on commercially available software for Document Control, perhaps Primavera Contract  Manager and Prolog.

Although I never liked P6 nor P3e, Primavera Expedition the precursor of Primavera Contract Manager in my opinion was good so I assume this product is good.  I recall it had an Insurance Log that included Dunning Notices so before expiring it would generate the warning and the Dunning Notices.

Needless to say that although common they are not exactly the same on every job therefore we can always learn something new by looking at what others are doing.

Good Luck,

Rafael

Ars J
User offline. Last seen 9 years 29 weeks ago. Offline
Joined: 1 Mar 2013
Posts: 8
Groups: None

actually it's better to say that I am looking for a document as procedure.

Ars J
User offline. Last seen 9 years 29 weeks ago. Offline
Joined: 1 Mar 2013
Posts: 8
Groups: None

Thank you very Much Rafael for your support.

By Variance Document, I mean a sample standard document to follow any change orders or variances that occure in the contract. This document may include some tables to trace the variances and chage orders.

Actually what you mentioned is the basic concept that every control project expert or project manager knows.

Regards,

Arsalan

Rafael Davila
User offline. Last seen 2 weeks 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5230

Variance or difference can be displayed in many different ways for almost all fields [not in order of preference].

  1. The first method that comes to my mind would be to disclose variance or field differences on the Gantt table.
  2. The second and my favorite is to show time distributed data using histograms. This will graphically display time distributed difference, very difficult and time consuming to mimic using difference fields that only show difference between current fields status and baseline/compared status at their respective DD.
  3. The third would be to generate variance trends, although not available in most software.
  4. Another would be to generate tabular reports to display field differences.

The following figure displays variance or field differences on the Gantt table as well as my favorite time distributed data using histograms.

 photo Variance_zpsd0add4a7.jpg

Good Luck,

Rafael