Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Setting up a 9//80 Calendar with Primaver v7

No replies
Katie Morris
User offline. Last seen 12 years 25 weeks ago. Offline
Joined: 4 Jun 2012
Posts: 2
Groups: None

Our construction crews have switched calendars mid project.

The original calendar was a Monday-Friday 8hr/day calendar.

The new Calendar is a 9/80

For those not familiar with a 9/80:

Week 1 Monday - Thursday 9hrs, Friday 8hrs and on

Week 2 Monday - Thursday 9hrs with Friday being a non work day.

 

My question pertains to how do I go about setting this calendar up in my project.

I will need to apply it to my remaining activities only.

I have created a calendar to modify, however, I get stuck on filling in the Time Period Units (hrs/day, hrs/week, etc)

I am fairly experience in using Primavera, however, this issue has me confused.

THank you for your help.

 

Katie