Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Critical activities more than non-critical

4 replies [Last post]
SM PUM
User offline. Last seen 10 years 36 weeks ago. Offline
Joined: 15 Nov 2011
Posts: 77
Groups: None

Hi planners

I have submitted a schedule to my manager and he has returned it with following comments;

Critical Activities are more than non Critical Activities. Try to minimize these critical activities.

 

Please Advice

Replies

Mike Testro
User offline. Last seen 33 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Hall

If you have a programme that has a start point and a clear cascade of tasks to an end point then there will be only one critical path.

If there is more than one CP then the chances of this occurring naturally are infinitesimal - therefore the most likely answer is the programme has been rigged.

You can of course have a number of such sectional cascades in a single programme.

Best regards

Mike Testro

Christopher Hall
User offline. Last seen 12 years 8 weeks ago. Offline
Joined: 17 May 2012
Posts: 42
Groups: None

Mike,

Good run thought.  Concurrent critical paths are, in circumstances, justifiable thou.

SM also check to see if you haven’t inadvertently imposed a project must finish by constraint earlier than planned/ forecast.

Chris

Mike Testro
User offline. Last seen 33 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi SM

You can start by removing all constraints that force criticality.

Next check how many tasks are set ALAP - they show critical even when there have lots of float.

After that look at what critical tasks remain and if more that 50% look to find out why -

First review any tasks more that 20 days long

Next check tasks with more than 1 outgoing link - are they all necessary?

Finally there an only be one critical path - if you have more than 1 youre programme has been rigged.

Best regards

Mike Testro

Christopher Hall
User offline. Last seen 12 years 8 weeks ago. Offline
Joined: 17 May 2012
Posts: 42
Groups: None

SM,

Your manager may be refering to the quantity of critical activities.  I.e. 3/4 of the programme may be critical, 1/4 non critical.

Depending upon your stance on such a broad brush approach to a programme review, the statement may be justified.

Chris