Hey folks its me with so many questions
Another major issue here please
I am currently working on a schedule with multidiscipline team of resources about to be allocated to tasks in crews. Currently the schedule has about 14 crews of various similar discipline all working together.
However, on the same schedule I have some tasks that has mix of people from each of these crews, for better illustration :
Task A work to be executed by Welding Team comprising 2 welders, 3 electricians and 1 mechanical technician all on 24hr shift
Task B – Installation Crewe - 2 Electrician, 1 Plumber and 3 Control engineer each on 12hrs shift
Task C - 2 Electrician from installation and 1 welder from welding team
Project Manager wants each resource person to be allocated to task individually in order to have an estimated budgeted labour units for each for the whole project
My concern - this a schedule of 1000 task and about 80 resources if allocated individually hence if I allocate manually the whole process could become cumbersome and tedious
Does anyone in the house has any idea of any fast rule to achieve same results with P6…. Am most grateful for any help I could get at this stage
Cheers
Replies