Dear Planning Planet,
I update our construction programme every week. Because of our poor performance on site the late finish was resulted to be sooner than the early fiinish. My story is when i made a 1 week look-ahead schedule the late finish date is impossible for the actiivity to finish as it gives only a remaining of 2 days for 1 acitivity to be finish. This 2 days is really impossible as per actual performance on site. Now, the project manager want me to move the late finish. I told them this happened because we are delayed. Project Manager want me to adjust the schedule.
Is it fine to change the start date / durations just to recover delays or change sequence of future activities when the site team wants it or just stick to the original schedule? This always happens to me everytime we are delayed in activity. Need help for the concept of planning specially on this kind of situation.