Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Planned% percentage Complete

1 reply [Last post]
Sajid Syed
User offline. Last seen 13 years 12 weeks ago. Offline
Joined: 7 Feb 2008
Posts: 56

Hi,

can some one comment on how to display  "Baseline % Complete" for activities as well as being summed up for the WBS levels as well.

the project is currently 50% into progress and "scheduled % complete"  values are not the same as the ones that i had initially calculated for the scurve from baseline.

Schedule%complete gives rescheduled values not the baseline values as i understand????

 

 

Regards

 

Replies

Mike Testro
User offline. Last seen 36 weeks 10 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Sajid

What software are you using?

Best regards

Mike Testro