Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Schedule Perfomance Index

3 replies [Last post]
Muthukumaru Senth...
User offline. Last seen 12 years 22 weeks ago. Offline
Joined: 9 May 2011
Posts: 25
Groups: None

How can we integrate Schedule Performance Index and Actual delay or ahead?

Replies

Gary Whitehead
User offline. Last seen 5 years 34 weeks ago. Offline

SPI is a good measure of actual performance. (Though I prefer to use SV myself, since this doesn't have the flaw of naturally trending towards 1)

In my opinion it is less reliable as a predictor of future performance, unless you a working on a very repeatable project like a pipeline.

It is certainly not a good way to predict project completion, since it takes no account of critical path or schedule risk.

 

Muthukumaru Senth...
User offline. Last seen 12 years 22 weeks ago. Offline
Joined: 9 May 2011
Posts: 25
Groups: None

Hi Gary;

Thank you for your reply.

As you mentioned , if we can not rely on the SPI for the delay analysis, what is the purpose to calculate the SPI??

Senthuran

Gary Whitehead
User offline. Last seen 5 years 34 weeks ago. Offline

How are you defining "actual delay or ahead"?

 

If you just mean forecast completion date vs target, I wouldn't integrate them. I have seen people dividing remaining duration by SPI to calculate a projected finish date,  but I don't think this is a reliable measure.

 

If you mean "how much work have we done vs how much we should have done", this is what SPI represents, so no need to integrate it.

 

If you mean an activity-count or activity-weeks type measure, just use SPI instead as it is a better measure of progress to date.