Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Man Hour Planning

1 reply [Last post]
Kumar Baiju
User offline. Last seen 10 years 43 weeks ago. Offline
Joined: 14 Feb 2011
Posts: 51
Groups: None

Hi friends

      I want to know the thumb rule for man power planning. For eample:- i am taking 35 hous for detail engineering for equipment design for A1 size, 72 Hous for stress analysis report and so on in my project .similarly i wnat to know the thum rule for construction and erection of steel structure ( manhour per tonne), cable laying ( manhour per metre), Piping erection ( Manhour per inch metre) etc. any refrence or guidence.

 

Regards\\

Replies

Maxime AUTHIER
User offline. Last seen 2 years 37 weeks ago. Offline
Joined: 21 Aug 2006
Posts: 13

Hi Kumar,

 

More info are required to naswer your question, indeed, steel erection ratio will not be the same for erection of stick-built structure or prefabricated pipe rack; manually cable pulling or with electrical winch, piping erection is also function of location (inside unit or on racks)... ... Maybe you can detailed your request

In addition, this will also be impacted by the country, either you know the local average productivity factor or you may need to adapt the ratio based on local feedback.

 

Also, did you look at the rates part of this site, it may contains some.

 

Rgds,

 

Maxime.