Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

production rates...

2 replies [Last post]
min joon sung
User offline. Last seen 15 years 12 weeks ago. Offline
Joined: 8 Apr 2010
Posts: 5
Groups: None
hi all,
i wonder if you have some ready made road schedule in primavera as a reference in preparing my construction schedule.
activities includes the following:
site clearance, cut & fill, stormwater, Curbs, elect. road crossing & street lighting, interlocking tiles, asphalt works, short term detours & traffic controls....

this is very urgent.
if you do, email it to thanks

Replies

Mike Testro
User offline. Last seen 30 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Only place one thread at a time.
Samer Zawaydeh
User offline. Last seen 6 years 17 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Min,

Your thread title asks for production rate, and you messages asks for a Schedule.

Read the drawings and the BOQs, specifications, etc and sit with your construction team, make a list of the activities, then start developing your schedule. This is the best way.

With kind regards,

Samer