production rates...

2 replies [Last post]
min joon sung
User offline. Last seen 14 years 19 weeks ago. Offline
Joined: 8 Apr 2010
Posts: 5
Groups: None
hi all,
i wonder if you have some ready made road schedule in primavera as a reference in preparing my construction schedule.
activities includes the following:
site clearance, cut & fill, stormwater, Curbs, elect. road crossing & street lighting, interlocking tiles, asphalt works, short term detours & traffic controls....

this is very urgent.
if you do, email it to thanks

Replies

Mike Testro
User offline. Last seen 22 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Only place one thread at a time.
Samer Zawaydeh
User offline. Last seen 5 years 25 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Min,

Your thread title asks for production rate, and you messages asks for a Schedule.

Read the drawings and the BOQs, specifications, etc and sit with your construction team, make a list of the activities, then start developing your schedule. This is the best way.

With kind regards,

Samer