hi every body,
i have submitted to may baseline for the CM for approval, this is Rivsion zero.
i finished the schedule 4 days earlier, and the CM have objectoin on that,we are goverened by fidic, isnt our right (contractor) to finish earlier if we want to.
2. i divided my schedule into MEP systems, then each system into fixes, 1, 2, and final. i consedered any pentration in walls or slab to be first fix. any after plaster of above False ceiling second fix, and final fix is the final fixtures. they object on this too wanting me to change conduites above false ceiling to be first isnt that second fix? what should i reply/
3. about resource allocation, for example i assigned 2 catogaries , one for my first package of the contract and other is for my second package, naming them: car1 and car2.
for each activty i assigned the proper carpenter.
to get resource allocation diagrame should i print the carpenter usage profile? but isnt that cummulative, i mean i need in the first day 1 car, in the second day 2 car, in third 1, so if they worked in the same zone the total number will be 2 carpenter, but if i used the usage profile in p6 it will show that i need 4 carpenter?
how can i get the total number of carpenters in the whole project ?
Replies