Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Relationship lines

1 reply [Last post]
Hengki Amri Roza
User offline. Last seen 15 years 38 weeks ago. Offline
Joined: 21 Jun 2008
Posts: 4
Dear planners,

I have a problem with relationship lines when I push F9 in my P5 schedule. The relationship lines didn’t follow the updated schedule but still at the baseline.

Anyone can tell me what is the wrong setting in my P5?

Regards,
Hengki

Replies

Arnold Puy
User offline. Last seen 9 years 32 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Hengki,

In View Menu --> Bars, move the Baseline Bars below the Current & Remain Bars by using “Shift up” & "Shift down” buttons.

HTH.

Arnold