Carbon steel productivity rate

1 reply [Last post]
kier legard
User offline. Last seen 14 years 48 weeks ago. Offline
Joined: 31 Jul 2006
Posts: 96
Groups: None

Hi to all,

Does anybody what is the productivity rate for prefabrication and erection of carbon steel in Kgs.


Regards,
kier

Replies

kier legard
User offline. Last seen 14 years 48 weeks ago. Offline
Joined: 31 Jul 2006
Posts: 96
Groups: None
Hi to all


Are these values correct.

Activity description kg/mh
PREF.PIPING > 2 C.S.(AV.32,98) 55.55200327
U.G PIPING C.S. (AVE.32,98 IN) 33.0002508
ER.PIP.A.G.>2 C.S.(AV.32,98IN) 41.66403672


Regards