item 3.5 on Page 12 gives some general guidance, but unfortunately the main advice is "it depends on the system". They do give guidance relative top known rates though, which might help you zoom in on an estimate. An alternative would be to contact 3 or 4 suppliers and take an average
Thank you for the information. At the moment the construction team and designer still have to decide which cladding system to be used. Until then I will have my best guesstimate to be put on the tender programme, which the rate is roughly 10 - 30m2 / day (presumed tiles to be used). This then will give me 10 weeks of installation.
Having spent 8 years putting various different types of cladding on buildings, I can say with some authority that it entirely depends on the design ... sorry. There are a few things that you can think about to zero in on a reasonable install rate though;
- Is it a custom designed or off-the-shelf screen?
- Is it a unitised system (panels are prefabbed off site and mounted to brackets fixed during structural works) or "stick system" where the wall arrives in bits and is assembled in place (and sometimes cut to size on site aswell)
- Is it all one "type" of cladding or do different elevations / levels have different designs?
- If it’s a unitised system, what are the standard panel sizes?
The cladding systems I worked with were all custom designs, if this is your circumstance you really need to study the design itself along with someone versed in installation to determine the install rate. Unitised cladding systems require very long lead-in times but the work on site can be in the order of a floor every 2 days for tower work. Stick systems usually require less lead-in but the site progress is slower. Cut on site stick systems, well...
If it’s an off the shelf system, The manufacturer should be able to provide guidance.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Have a look at;
http://www.engineering.leeds.ac.uk/civil/research/cae/current/cimclad/R…
item 3.5 on Page 12 gives some general guidance, but unfortunately the main advice is "it depends on the system". They do give guidance relative top known rates though, which might help you zoom in on an estimate. An alternative would be to contact 3 or 4 suppliers and take an average
James,
Thank you for the information. At the moment the construction team and designer still have to decide which cladding system to be used. Until then I will have my best guesstimate to be put on the tender programme, which the rate is roughly 10 - 30m2 / day (presumed tiles to be used). This then will give me 10 weeks of installation.
Thanks.
Danang,
Having spent 8 years putting various different types of cladding on buildings, I can say with some authority that it entirely depends on the design ... sorry. There are a few things that you can think about to zero in on a reasonable install rate though;
- Is it a custom designed or off-the-shelf screen?
- Is it a unitised system (panels are prefabbed off site and mounted to brackets fixed during structural works) or "stick system" where the wall arrives in bits and is assembled in place (and sometimes cut to size on site aswell)
- Is it all one "type" of cladding or do different elevations / levels have different designs?
- If it’s a unitised system, what are the standard panel sizes?
The cladding systems I worked with were all custom designs, if this is your circumstance you really need to study the design itself along with someone versed in installation to determine the install rate. Unitised cladding systems require very long lead-in times but the work on site can be in the order of a floor every 2 days for tower work. Stick systems usually require less lead-in but the site progress is slower. Cut on site stick systems, well...
If it’s an off the shelf system, The manufacturer should be able to provide guidance.
hope this is of some help