How primavera shows retention money deduction

1 reply [Last post]
Haresh Jayanth
User offline. Last seen 6 years 21 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219
For any project, in primavera 3.1 how can we show receipt of Advance Payment at the start of the project and also deduction of retention money every month from very running bills in a cash flow.

Kindly explain how primavera will show deductions from RA bills in a cash flow??????

Replies

MK TSE
User offline. Last seen 4 years 6 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
Consider by resource instead of cost.
When update, the actual completion amount will include the advance payment.
The To completion value is less the retention
However, creat one more activity for collecting the retention