Change in base program.

1 reply [Last post]
Santhosh kumar Na...
User offline. Last seen 6 years 49 weeks ago. Offline
Joined: 7 Aug 2006
Posts: 66
The target plan is "Approved with comments" based on that i started updating the progress. But in reply to the above said comments, my boss is asking to introduce an activity with the the duration equal to delay by owner / client in target for a revised target ( some times want to chnage the links also) every month or occurance of any delay and i have to do the update based on new revised non approved target. I believe these delays or stoppage can be incorporated in updates (mention the reason in log record for tracability) and revised target can be submitted after 1 year or mid of project with all the accumulaed delays!!! whts ur suggession!!!!

Replies

Nigel Winkley
User offline. Last seen 31 weeks 6 days ago. Offline
Joined: 11 May 2006
Posts: 187
Groups: The GrapeVine
Santosh

I did a quick fix a while ago.

I did as your PM requested and added a bar for the delay. This was then linked to the other activities retaiining the original logic as well. All activities were then ’delayed’ by the new bar and when the delay was complete they re-started.

Yes, I know it is messy and probably not ’good practice’ but it took ten minutes and got me out of a hole!

Cheers

Nige