Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Efficiency

2 replies [Last post]
Radhakrishnan Gun...
User offline. Last seen 16 years 14 weeks ago. Offline
Joined: 12 Dec 2004
Posts: 8
Groups: None
Hi,

Can any one suggest how to calculate the % efficiency in a project, based on Budgeted man hour, Actual consumed man hour, Planned man hour and progress percentage!!!

Thanks in advance.
Guna.

Replies

Philip Jonker
User offline. Last seen 16 years 11 weeks ago. Offline
Joined: 7 Nov 2004
Posts: 852
Groups: None
Hi Radhakrishnan ,

Performnce is not not normallly measured by % but by factors, such as , ,97, the simple rule is these factors are used in cost to completion calculations

Gary Whitehead
User offline. Last seen 14 years 5 weeks ago. Offline
Joined: 1 Sep 2005
Posts: 69
Groups: None
Sounds like a job for Earned Value!

Earned Value = Budgeted cost x progress percentage

Schedule efficiency (or schedule performance index) = Earned Value / BCWS (budgeted cost of work scheduled)


Cost efficiency (or cost performance index) = Earned Value / ACWP (actual cost of work performed)


So using the data you list, I’d suggest:

(Budgeted man hour x progress %) / actual consumed man hour