Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Raft Foundation Construction

8 replies [Last post]
Alan Burns
User offline. Last seen 19 years 5 weeks ago. Offline
Joined: 16 Jul 2004
Posts: 17
Groups: None
Hi all,

Does anyone have any detailed information on what they view as the correct sequencing for the construction of a raft foundation, the project is a £6 million steel framed school. There is great debate in our office at present!!

Hope someone can help,

A.

Replies

Darrell ODea
User offline. Last seen 18 years 33 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 174
Groups: None
Roger,
Would you believe that I knew someone would support my comment. Don’t know why.

Pre-fabricate everything. They had the right concept in mind in the 60’s, with system building.

D.
Roger Thomas
User offline. Last seen 14 years 1 hour ago. Offline
Joined: 30 Jun 2003
Posts: 15
Groups: None
Many a true word said in jest Darrell. The foundations for the cills in the Thames Barrier were constructed in dry dock and then floated into position.
Darrell ODea
User offline. Last seen 18 years 33 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 174
Groups: None
Don’t forget to make it out of wood or plastic, it floats better that way.

Prefabricate it off site & just deliver & position.

QED
Dayanidhi Dhandapany
User offline. Last seen 3 years 26 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
To avoid all these doubts of underground services/deep fdns etc., develop the construction schedule sequence based on the construction drawings.
Asif Anwar
User offline. Last seen 8 years 15 weeks ago. Offline
Joined: 1 Oct 2004
Posts: 39
Groups: None
Don’t forget to allow for any temporary works required especially if it is a deep foundation.

Asif
Jaco Stadler
User offline. Last seen 17 years 50 weeks ago. Offline
Joined: 9 Sep 2004
Posts: 299
Groups: None
What about underground services. Ducts etc.

A Simple rule is from bottom to top.
Alan Burns
User offline. Last seen 19 years 5 weeks ago. Offline
Joined: 16 Jul 2004
Posts: 17
Groups: None
Think I may have won the arguement my friend, thanks!
Dayanidhi Dhandapany
User offline. Last seen 3 years 26 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
If you have construction drawings for the raft foundation(for an example), you can develop the construction sequence.

If you have divided the raft area into some zones, then for any zone the probable construction sequence would be

Excavation->Blinding->Reinforcement->Sideformwork->Concreting->Curing->RemovalofFormwork and then based on the design/drawing if you have steel column works, you can develop the program further as provision for fixing of base plates(before concreting), steel column members etc...............