I feel it depend from planner to planner. If the planner knows the scope and the know how he can do it on his own.
I follow the steps below
1) I normally familirised myself with the scope first. (I have found speeking to each induviduel in the team helps a lot with this)
2) Then I draw up a draft schedule and discuss/Agree it with each team member.
3) The I Issue it for approval to each member
4) Then I issue it to the PM for approval.
5)Once he have approved it I start cutting back time by activity with each team member. This normally make sure that we are ahead of our original baseline schedule approved by the project manager.
I believe it is essential that the all of the project team are involved in, and contibute to, the programme at the earliest possible stage. I find that where some members of the team are reluctant to provide their thoughts then it is best to prepare a draft programme for them to comment on. This will start the ball rolling and hopefully constructive comments will be forthcoming. As a Project Manager there is nothing worse than trying to keep to a schedule that you have not been consulted on. Discussion will foster more committment from those responsible for ensuring the schedule is met. Good luck!
The best method is to let the whole team to prepare the program putting all the essential components ( 4M + C). 4 M means - 1. Material 2. Manpower 3. Machine and 4. Method. and last is C - COMMITMENT
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Roger, Jaco,
The methods you both suggest support fully my own method!
Kind Regards,
Alan.
I feel it depend from planner to planner. If the planner knows the scope and the know how he can do it on his own.
I follow the steps below
1) I normally familirised myself with the scope first. (I have found speeking to each induviduel in the team helps a lot with this)
2) Then I draw up a draft schedule and discuss/Agree it with each team member.
3) The I Issue it for approval to each member
4) Then I issue it to the PM for approval.
5)Once he have approved it I start cutting back time by activity with each team member. This normally make sure that we are ahead of our original baseline schedule approved by the project manager.
I believe it is essential that the all of the project team are involved in, and contibute to, the programme at the earliest possible stage. I find that where some members of the team are reluctant to provide their thoughts then it is best to prepare a draft programme for them to comment on. This will start the ball rolling and hopefully constructive comments will be forthcoming. As a Project Manager there is nothing worse than trying to keep to a schedule that you have not been consulted on. Discussion will foster more committment from those responsible for ensuring the schedule is met. Good luck!
The best method is to let the whole team to prepare the program putting all the essential components ( 4M + C). 4 M means - 1. Material 2. Manpower 3. Machine and 4. Method. and last is C - COMMITMENT
HOPE THIS WILL HELP.