Cost Loading in P3

1 reply [Last post]
Forum Guest
User offline. Last seen 40 weeks 13 hours ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Dear PPers,

I expect someone can clearly explain to me with some example on how the lumpsum contract value is been distributed to detailed activities in P3.


T.Q

Guest

Replies

Morteza Jafari
User offline. Last seen 12 years 41 weeks ago. Offline
Joined: 20 Jul 2003
Posts: 33
the first I suggest to login to this site and be a permanant member, it will help you very much,
in response your query, I can summeraize my comments as follows:
lumpsum contract usually have a price/cost breakdown and this breakdown come in table and define elements of cost of project including engineering, procurement, construction and so on, if bidding be a completted package, it will certinally be in package, based on this table you should develop detailed price and input in P3.
I hope the above is clear.