Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Cost breakdown

7 replies [Last post]
Ali Hamouda
User offline. Last seen 8 years 24 weeks ago. Offline
Joined: 3 Feb 2002
Posts: 109
Groups: None
what about cost breakdown for the activities? is it possible to breakdown the cost at the instant that the contract price is lumbsum value? can we do break for the cost to include overhead,Material,Labour and equipment? constructive discussion would be appriciated? thanks Ali -------------------------------

Replies

Quazi Asaduddin
User offline. Last seen 13 years 23 weeks ago. Offline
Joined: 22 Oct 2005
Posts: 10
Groups: None
The Contract is Lump sum or Unit Rate at the tender Level. When contractor is to start the execution of the project he must have the detail BOQ Of the Project Scope prepared by either Consultant or by the contractor based on the information avialble at that stage at least Project Drawings and specifications.

Once we have the detail BOQ with unit rate we can make the Cost Breakdown as we need. For Lump sum contracts contractor should prepare the detail BOQ as soon as the contract awarded to him to know the Project Budget with Overhead and Profit.

Quazi Asaduddin.
Hernando Pesca
User offline. Last seen 17 years 7 weeks ago. Offline
Joined: 23 Apr 2007
Posts: 24
Groups: None
Ali,

In my company, lump sum conract has always its cost breakdown. It comes from the sum of pay items, and each pay item has its unit rate. We derive the rates from "selling rate=BC(material)+BC(labor)+BC(equipment)+OH&P". The overheads (direct & indirect) are defined, and the margin as well.- If you have the cost breakdown, it would be easy during preparation of schedule and in procurement process.

Going back to the questions of Ernesto...unit price contract are usually on EPC projects with no final design.

Regards,

Hernan
A D
User offline. Last seen 3 years 51 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Even though the Lumpsum projects doesn’t reflect the unit prices for the items, it doesn’t mean that pricing is done on parametric estimating or it is just analogous.

The project is broken down into various work packages (where cost can be monitored) and cost coding is done for each item. Especially, for Lump sum contracts, we need to make a Pre-Start Estimate (PSE) for the project. And based on the cost to be incurred, a commitment is given to the top management, in terms of profit margin (say, 8%, 9% etc.)

For each cost coding, rate analysis is done covering manpower, machinary and material. From all the items, estimate the total expenses incurred. Add Overheads (Site & HO), and other sundry items to the total.

Compare the initial cost considered (while estimating) with this cost and calculate the profit margin to be comitted.

Hope it is clear.

Thanks,

Raviraj A Bhedase
mimoune djouallah
User offline. Last seen 5 years 15 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388
Ernesto

in our country mainly all contracts are unit price,due to the fact that when you bid for a state project( which represent the majority of the market), the bills of quantities and the drawing are really very poor ( technically speaking) in this case the unit price is the best type of contract, the lump sum ones are only used for oil and Gaz project.
ulysses garcia
User offline. Last seen 13 years 40 weeks ago. Offline
Joined: 22 Aug 2005
Posts: 259
Groups: GPC Qatar
Eventhough the contract is cost lumpsum basis you can break it down into each activity by using weight percent to each. ie ( based on duration, resources, or units)
Ernesto Puyana
User offline. Last seen 8 years 10 weeks ago. Offline
Joined: 12 Jan 2001
Posts: 111
Groups: None
Let me ask these questions to try and open up the discussion on this issue: To what extent is the unit price contract used worldwide? in what kind of projects? Do you used the unit price system when estimating a lump sum project? if not, how do you do it?
Tomas Rivera
User offline. Last seen 5 years 32 weeks ago. Offline
Joined: 2 May 2001
Posts: 139
Groups: None
I will try to be constructive. I am not sure what your concern is; but yes, of course you can breakdown the lump sum cost by activity, if you have the lump sum estimate breakdown. Just bear in mind that you might need to distribute part of the overhead directly to activities and part to a new activity that stretches along the project timeframe for overhead that depends on time elapsed (like site office overhead).