Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Commissioning

2 replies [Last post]
Roy André
User offline. Last seen 20 weeks 2 days ago. Offline
Joined: 26 Feb 2024
Posts: 5
Groups: None

Hello,

Am I the only one who find it challenging with the commissioning phase? Is there anyone that have some "best-practice" or experience with this?

Replies

Liu Yi
User offline. Last seen 4 weeks 6 days ago. Offline
Joined: 12 Feb 2011
Posts: 12

hi Roy,

I am intresting about the commissioning schedule. there are some understanding based on my experience.

  1. Classfy the system or subsystem based on the process, this work need process engineers support.
  2. Confirm the input and output for each subsystem or system to classfy the sequence.
  3. Based on the commissioning strategy/plan (e.g. if purcashe outer material etc.), make the commissioning works / schedule.     
Liu Yi
User offline. Last seen 4 weeks 6 days ago. Offline
Joined: 12 Feb 2011
Posts: 12

hi Roy,

I am intresting about the commissioning schedule. there are some understanding based on my experience.

  1. Classfy the system or subsystem based on the process, this work need process engineers support.
  2. Confirm the input and output for each subsystem or system to classfy the sequence.
  3. Based on the commissioning strategy/plan (e.g. if purcashe outer material etc.), make the commissioning works / schedule.