Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

because constraints not allowed, contractor put in new calendars that do the same thing...

No replies
John Reeves
User offline. Last seen 8 weeks 5 days ago. Offline
Joined: 10 May 2013
Posts: 344
Groups: None

because constraints not allowed, contractor put in new calendars that do the same thing...Contractor has kicked work out to spring due to weather, some thought that making them remove the start constraint would force them to pull up the dates, instead they just put it on a new craft calendar that held the same date.  I assume due to means and methods - there is not much that can be done.  We could have the produce a resource planning report, but when they do not hit then number of crews or workers - it will be too late to bring it back in.

John Lau
User offline. Last seen 39 weeks 21 hours ago. Offline
Joined: 11 Jan 2022
Posts: 6
Groups: None

How would you show potential risk incurred by poor weather condition in the schedule?

Would you prefering a single contingency activity at the end of the schedule stating it's used to account for all potential risks?

John Lau
User offline. Last seen 39 weeks 21 hours ago. Offline
Joined: 11 Jan 2022
Posts: 6
Groups: None

How would you show potential risk incurred by poor weather condition in the schedule?

Would you prefering a single contingency activity at the end of the schedule stating it's used to account for all potential risks?

david kelly
User offline. Last seen 1 week 2 days ago. Offline
Joined: 12 Feb 2016
Posts: 39
Groups: None

Contractors do what the contract allows them to. The hint is in the nane 'contractors'.  In my experience the easiest way to improve 'owner' project controls, is to throw out the 30 year-old clauses in contracts they issue that describe the contractor's planning obligation, and rewrite them.