Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

help : activities total float is increasing by decreasing the remaining duration for the activates

5 replies [Last post]
mohammed mowafy
User offline. Last seen 4 years 19 weeks ago. Offline
Joined: 17 Feb 2021
Posts: 5
Groups: None

hello all ,

i'm working on a big schedule it's about 20,000 activites  and by updating it
i usually notice that  for some linked activtes package  the activity total float is increasing by decreasing the remaining duration for the activates .

i will explain  it more as there is progress on site i update the progress percentage complete for the activity and also decrease the remaining duration ( physical type) and then the finish date for the linked activites shifted to be more than the current date instead to be less 


noting that i don't use leds or level of efforts activites and neither SF relationship  (only SS and FF  or FS relationships)

and the activites don't have any ONGOING OR NOT STARTED predessesor only the relationships between them selves 

thanks in advance 

Replies

Zoltan Palffy
User offline. Last seen 2 weeks 9 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

1. 1st update the activites that have started with actul start dates but not finished and put in the remaining duration for each of those

2. If activites here started before and have now finished put in the actual start date.

3. If an activity has started AND finished put in the actual start AND actual finsh date 

4. Press F9

5. Chnaae the dated date to reflect the date that you are recording progress thru

6. Analyse results

mohammed mowafy
User offline. Last seen 4 years 19 weeks ago. Offline
Joined: 17 Feb 2021
Posts: 5
Groups: None

i,m updating it 
 i changed the data date also 
i will explain more i  updated the activites and reduce the remaining duration then changed the data date from 31-01-2021 to became 15-02-2021 

thats mean 15 days working day which give me increase at the total flot by -18 days  and if i decresed the remaning duration for certain activites the total flot increase also to become -20 

mohammed mowafy
User offline. Last seen 4 years 19 weeks ago. Offline
Joined: 17 Feb 2021
Posts: 5
Groups: None

i,m updating it 
 i changed the data date also 
i will explain more i  updated the activites and reduce the remaining duration then changed the data date from 31-01-2021 to became 15-02-2021 

thats mean 15 days working day which give me increase at the total flot by -18 days  and if i decresed the remaning duration for certain activites the total flot increase also to become -20 

Rafael Davila
User offline. Last seen 20 weeks 1 day ago. Offline
Joined: 1 Mar 2004
Posts: 5241

20,000 activities schedule is for an experienced scheduler.

Are you updating the schedule or you mean revising current schedule version?

Zoltan Palffy
User offline. Last seen 2 weeks 9 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

are you changing the data date also ?