Hi all,
probably more aimed at P6 administrators...
I've been using P6 for monthly reporting for a long time now. Simple process of opening all relevant plans, then runnning a saved reort to output remaining early units by Activity ID. This month, all has gone wrong, but nobody has altered the reports at all. No matter what I do, P6 assumes I had dozens of other plans open (even if I only have one open at the time), and also won't output activity IDs.
Usual format is:
12345 |
C0101M.001 Procurement |
Material expenditure only |
Subtotal |
INFL.Bal Balance of Inflation - Escalation |
Contingency |
Subtotal |
C0101M.003 Procurement For Fixtures and Fittings (needs Parts list from Design) |
Material expenditure only |
Subtotal |
C0101M.005 Procurement For Manufacture |
Material expenditure only |
Subtotal |
But now it's outputting as:
12345 |
(12345) (Project Title) |
Material expenditure only |
Contingency |
Subtotal |
Any ideas befor eI ask our IT guys to remove and reinstall? Other users can run reports absolutely fine!
Thanks
Replies