replacement for the SDK in later versions of P6

Hi

we are (finally) moving from P6.7 to 6.17 and I have noticed in preparing the migration that Pv no longer supports SDK in later versions of P6. I see no Pv provided replacement as yet (but may have missed it). Is there a recommended replacement, either Pv/Oracle provided or 3rd party? Specifically, I will miss the ability to build and manipulate activity code libraries and WBS structures

or am I going to have to take the plunge and learn to code the API?

cheers

James