Brazilian project in Portuguese - what are Pontos?

1 reply [Last post]
John Reeves
User offline. Last seen 9 weeks 3 days ago. Offline
Joined: 10 May 2013
Posts: 344
Groups: None

I know pontos means points.  There is a different HH for manhours.  But also under resouces is "pontos".  I don't know if I should count them towards hours, or if they are Indirect hours?  If I leave them in the rate seems too high, if I remove them the rate seems too low.  Any ideas?