P6 Not Exporting Full Cost Account ID

7 replies [Last post]
Coy Laughlin
User offline. Last seen 4 years 38 weeks ago. Offline
Joined: 13 Nov 2019
Posts: 4
Groups: None

I am trying to export the entire cost account ID into excel. It appears as if primavera only takes the end value of the ID. So if I have a cost acount ID 00A.01 it will only export 01. Is there any way around this? 

Replies

Zhang Haixiang
User offline. Last seen 3 years 44 weeks ago. Offline
Joined: 14 Apr 2005
Posts: 250
Groups: None

 

you can try report. 

* create a "activity resource and role assignments" report to include the cost account column

* run the report and save to an ASCII Text File

* import the file into Excel

Coy Laughlin
User offline. Last seen 4 years 38 weeks ago. Offline
Joined: 13 Nov 2019
Posts: 4
Groups: None
Yes. The cost account ID only exports the end value so 316.0.10.4 will only export .4 I dont know how to format the cost account ID to get a successful re-import. I am exporting to excel.
Zoltan Palffy
User offline. Last seen 20 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

so you are exporting Resources and Resource assignments ?

then you are exporting resource id and and cost account id ?

and resource type ?

David Kelly
User offline. Last seen 2 years 2 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

I have a few versions of P6 on different machines, but none as old as 7.0

I would advise downloading an evaluation of version 18 PPM, and checking it with an import of your project.

Coy Laughlin
User offline. Last seen 4 years 38 weeks ago. Offline
Joined: 13 Nov 2019
Posts: 4
Groups: None
I checked the admin preferences and both items you specified were set to the maximum. Also, I am using version 7.0.
Zoltan Palffy
User offline. Last seen 20 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

do you have the rights to do this ?

what version of p6 are you using ? 

in the data limits what are your cost account tree maximim level set to  ?

in your ID Lenghts what are your cout account ID maximim characters set to  ? The maximum is 20 make sure that is set to that

 

David Kelly
User offline. Last seen 2 years 2 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

works for me...