Curved Data Date - why? what? when? is it for?

2 replies [Last post]
John Reeves
User offline. Last seen 28 weeks 2 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

I am used to seeing a straight data date line. Lately I been seeing curves data date lines, ie curved out around certain activities.  I assume this is from a setting, and after googling it with-out getting an easy answer I am asking you.  What does it represent?  Where is the setting for it?

Replies

Zoltan Palffy
User offline. Last seen 1 day 11 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

click on the crooked progress line icon and it wil be a straigh line.

 

7096
progress_line.gif

 

John Reeves
User offline. Last seen 28 weeks 2 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

OK, not that hard to solve, it is the "Progress Line" which overlays the Data Date line.  Obviously I didn't use it much prior.  I kind of assumed it was something like that but here is a confusing aspect.  I don't have a Baseline attached to that schedule - so how can it be telling me how ahead or behind the dates are - meaning how can the line be crooked?