Same resource - but different pay rates

J
J Ram 👤 Member for 7 years

Hello everyone,

I'm new to this forum as well as new to Primavera P6. My question is regarding assigning different rates for the same resource. So let's say we have a job starting on June 1st, 2019 for an Outside Machinist at a rate of $58 / hour, but we also have the same Outside Machinist working on another job on June 1st, 2019 but at a different rate of $60 / hour. Is there a way to incorporate this onto a schedule to reflect it's budgeted labor cost or is there an alternate way? The reason why I'm trying to do this is because I want to have a Master Schedule that shows all work and the resources assigned, but the same resource works at different rates.

 

Thanks for the help!

J
J Ram 👤 Member for 7 years

Thank you both the help. I'll mess with a few things and hopefully this solves what I need.

R
Raymund de Laza 👤 Member for 16 years 7 months

Set the Effective Dates and Time for each Rate in the Units & Prices Tab of the Resources.

Featured Partner

Top Posters

Tijo Kurian
11 posts
Zainab El-Beialy
3 posts
Kamlesh Parmessur
4 posts
MR JUDE C ANYAEGBU
0 posts
GeoVe
0 posts
Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts