As a bigenner planner, I have made a plan for a client as two projects, the start and finish dates for one of them are the actuals. whereas the start and finish dates of the other one are the planned ones, then I maintained the latter as a baseline to the first one, the client did not accept it and asked to modify that, he has also mentioned that the project is full of constaints. Are there any other ways to follow?
Full of Constraints
Forum Sponsor
Top Posters
Syed Shoeb
0 posts
Viet Tran
8 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
glad I could help
Many thanks, the problem has been solved
the only activities that should have constraints are CONTRACTUAL milestones
also the project must finish by date should be set
Suhaib,
do you mean: you don't use activity relationship, but only activty constraints to schedule your project?
you should not have any other date constraint that the project start date and the contractual finish date
Alexandre