Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Changing the Resource Type

1 reply [Last post]
Kannan CP
User offline. Last seen 50 weeks 6 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

In a Programme, all the equipments are assigned as Labor type, by mistake. While trying to change the type in the Resource Pool, it is showing the message as Not Possible to Change. Tried the Global Change and unsuccessful.

 

Any solution to rectify it.

Regards

Kannan

Replies

Zoltan Palffy
User offline. Last seen 1 week 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

copy existing resource info to excel 

create a new resource

delete old resource

assign new resource

export new resource and budgtes to excel

populate new resource budgets with info form old resource budgets

import new resoruce budgets