Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Updating over 7000 Activities in p6

1 reply [Last post]
Mohammad Zakaria
User offline. Last seen 7 years 25 weeks ago. Offline
Joined: 18 May 2017
Posts: 3
Groups: None

Hello Everyone,

I'v created baseling schedule contains over 7000 activities. I have to update them now by activity % complete. Is there and fast way to update them by excel if I have the data already in excel?

Replies

Zoltan Palffy
User offline. Last seen 16 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

yes export the activites to excel you will need to export the actual start field, actual finish field and either the remaining duration and or the duration % complete.

Progress 2 activities manually in P6 progress one that has started but has not yet finished and progress another one that has started AND finished use to see the format that is expected for the input data.

The actual start TIME and the actual finish TMES must be included in the import.