import/export activity code

3 replies [Last post]
Jason LI
User offline. Last seen 4 years 7 weeks ago. Offline
Joined: 1 Jan 2008
Posts: 37

Dear All,

I'm preparing the schedule by system, using activity code. there are thousands of system and subsystem, are there any quick way to import/export the activity code from excel.

 

thanks

Replies

Zoltan Palffy
User offline. Last seen 20 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

this is a 2 step process

step 1 is buildign the activity code dictionary. The fastest way to build this is by using SDK

step 2 is populating the activites with the proper code value. The fastes way to do this is to export all of the activities along with the code fields  and then populate the code value fields in excel and import the excel file back into p6

Emad Mofarej,PMP,...
User offline. Last seen 3 years 16 weeks ago. Offline
Joined: 18 Feb 2012
Posts: 39
Groups: None

OR XERfileparser

However if you want to transfer activity codes from a project to another you can use update baseline function in P6

wullie hendry
User offline. Last seen 7 years 15 weeks ago. Offline
Joined: 14 Oct 2014
Posts: 8
Groups: None

Use SDK